建設記録

Construction record
PointA PointB PointC PointD PointE PointF PointG
25May2015

A煙突Stack

2015/5/25 スラグ(石炭灰が溶融・固化したもの)搬送・貯蔵設備の基礎工事が始まりました。桟橋手前にスラグ貯蔵倉庫、石炭ガス化設備から貯蔵倉庫に向かってスラグ移送コンベアが建設されます(右)。排熱回収ボイラ(中央)から煙突に向かう煙道が間もなく繋がります。 The foundation work of the slag (melt and solidified coal) transfer/storage equipment was started in May 25, 2015. Slag storehouse will be constructed in front of the pier, and a Slag conveyor will be constructed between the Coal Gasification Unit and the storehouse (right). The Duct that stretches from the Heat recovery steam generator (center) to the chimney will be connected soon.